Progress of C-6 expansion and upgrading
The recent news about the groundbreaking for the C-6 expressway led some people to this site and looking for information on C-6. Here are more photos I took last month (January 2018):
The future northbound lanes of C-6 is currently under rehabilitation and are being upgraded to Portland cement Concrete Pavement (PCCP). The new southbound lanes currently serve the two-way traffic.
The sign is an old one and perhaps still in use as a barrier more than for information
You see a lot of people jogging, walking and cycling along the finished road. It shows the demand for spaces for such activities, including recreation, and a similar situation may be observed along C5 before and along the perimeter of Libingan ng mga Bayani where a lot of people do exercises and other activities along road sections that are closed to vehicular traffic.
With one lane completed the second lane is prepared for pouring of concrete. You can see the formworks along the median.
Other sections have yet to be prepared for concreting but have been stripped of the old pavement (Asphalt Concrete pavement or ACP).
What you see here at right is the compacted base/sub-base layer. The forms have not been installed yet.
Backhoe and roller at the worksite.
A grader in action.
I will post more photos later from the next time I pass by the area. From what I’ve hear so far, traffic has eased along the expanded Barkadahan Bridge but there are still bottlenecks to address along this alternative route. There will also be a need to have a higher capacity, less friction connection between C-6 and C-5 as traffic along C-6 increases and it’s become quite obvious that Taguig’s narrow streets cannot handle this increasing travel demand between the two highways. It makes sense to have a higher quality, limited access road for this purpose since Taguig roads are already congested and through traffic poses a safety hazard to the residential areas where vehicles travel through.
–